Berrings NS Phase 1

Project: Extension to Berrings National School

Client: Board of Management, Berrings National School, Berrings, Co.Cork.

Main Contractor: Murphy Commercial

Value: € 375k

Contract Duration: August 2008 – March 2009 (9 Months)

Architects/Consulting Engineers: Denis Moran Design Ltd., Berrings, Co.Cork

Description: New 3800 sq.ft. school extension comprising 3 no. classrooms, resource room, mechanical & electrical fit-out, modifications to existing building and all associated site works.