Berrings NS Phase 1
Project: Extension to Berrings National School
Client: Board of Management, Berrings National School, Berrings, Co.Cork.
Main Contractor: Murphy Commercial
Value: € 375k
Contract Duration: August 2008 – March 2009 (9 Months)
Architects/Consulting Engineers: Denis Moran Design Ltd., Berrings, Co.Cork
Description: New 3800 sq.ft. school extension comprising 3 no. classrooms, resource room, mechanical & electrical fit-out, modifications to existing building and all associated site works.